What is expiring in March 2027
Two Atlas Tube EPDs hit their expiry on March 22, 2027. They are titled Hollow Structural Sections and Fabricated Hollow Structural Sections, originally issued March 22, 2022 under UL as product‑specific Type III declarations covering HSS made across multiple Atlas sites. California’s public EPD list confirms the 3/22/2022 to 3/22/2027 window (Caltrans EPD List, 2026).
Are replacements already published
Yes. Atlas has rolled out a suite of facility‑specific EPDs that cover the same HSS products, with issue dates in 2024 and 2025. Examples include Birmingham, AL; Chicago, IL; Plymouth, MI; Blytheville, AR, plus a Blytheville JUMBO scope; Harrow, ON with both average and EAF‑only mix; and Kansas City, MO. These are UL‑verified and valid into 2029 or 2030 based on their individual issue dates.
Quick links to representative PDFs on Atlas’ site:
- Birmingham, AL (valid to 2029‑08‑14): https://www.atlastube.com/resource-library/environmental-product-declaration-birmingham-al/
- Chicago, IL (valid to 2029‑08‑14): https://www.atlastube.com/resource-library/environmental-product-declaration-chicago-il/
- Plymouth, MI (valid to 2029‑08‑14): https://www.atlastube.com/resource-library/environmental-product-declaration-plymouth-mi/
- Blytheville, AR including JUMBO (valid to 2029‑08‑14): https://www.atlastube.com/resource-library/environmental-product-declaration-blytheville-ar/ and https://www.atlastube.com/resource-library/environmental-product-declaration-blytheville-ar-jumbo/
- Harrow, ON average and EAF‑only (valid to 2029‑07‑15 and 2029‑09‑09): https://www.atlastube.com/resource-library/environmental-product-declaration-harrow-on/ and https://www.atlastube.com/resource-library/environmental-product-declaration-harrow-on-eaf-only/
- Kansas City, MO (valid to 2030‑07‑14): https://www.atlastube.com/resource-library/environmental-product-declaration-kansas-city-mo/
These replacements keep the scope familiar to specifiers. The new PDFs also share cradle‑to‑gate values for unfabricated HSS, which many submittal reviewers ask for.
Book a free 30-min. consultation
Discuss ideas to mobilize your EPDs, review your portfolio, and generate strategies to make LCA insights impactful across your organization.
What actually changes for specifiers
Think of the older pair as umbrella EPDs. The new set is a row of clearly labeled, facility‑specific umbrellas that are easier to match to mill certificates and purchase orders. Update binders and procurement notes to reference the plant‑level UL numbers. If a project submittal still cites the 2022 documents after March 2027, swap in the corresponding current PDF from the Atlas resource library links above.
If a gap emerged, who would fill it
Competitors in HSS have valid, recent declarations and would be natural fallbacks on EPD‑required jobs. Two examples that are current during 2026 and beyond:
- Nucor Tubular Products HSS EPD, updated in 2024 and valid into 2029, covering multiple NTP facilities under UL verification (Nucor Tubular HSS EPD, 2024). (PDF)
- Bull Moose Tube Unfabricated Low‑Embodied Carbon Steel Pipe and Tube, issued Nov 27, 2024 and valid to Nov 26, 2029 under SCS Global Services (SCS Global Services, 2024). (PDF)
Why timely renewal still matters
EPDs are typically valid for five years, which is why the 2022 pair times out on March 22, 2027. Even with replacements available, many owners and LEED v5 reviewers expect the most current product‑specific EPD referenced by link or file name. If a submittal points to an expired document, reviewers may default to conservative carbon assumptions that make your product look worse on paper, or they may ask for a substitution, both of which cost time.
Fast checklist for AEC teams this quarter
- Replace any references to the 2022 Atlas Tube EPDs with the plant‑specific PDFs linked above.
- Capture the UL declaration numbers and validity dates in your spec notes. For example, Kansas City, MO runs to 2030‑07‑14; several 2024 issues run to mid‑2029.
- Keep a backup plan. If procurement tightens, the Nucor and Bull Moose EPDs listed here are broadly accepted in HSS scopes (Nucor Tubular HSS EPD, 2024; SCS Global Services, 2024).
Extra context for product managers
Atlas’ older umbrella EPDs listed multiple sites in one document, which helped speed adoption in 2022. The 2024–2025 refresh pivots to individual facilities, which is cleaner for audits and mill traceability. If your internal teams track submittals in a PIM or QMS, map each SKU to the correct plant PDF. It sounds fussy, yet it prevents those small, last‑mile snags that slow down awards. And it is definitley worth the hour.
For a market snapshot of HSS EPD activity, see this neutral overview on the US hollow sections landscape: EPDs for Hollow Sections in the United States.
Bottom line for March 2027
Two legacy Atlas Tube EPDs expire on March 22, 2027, but practical risk is low because plant‑specific UL‑verified replacements are already live and stretch to 2029 or 2030. Refresh your references now so bids, submittals, and closeouts keep moving without friction.