How EPDs Travel: Spec to GC to Submittals
Specs might name the brand or list three acceptable manufacturers. Then reality hits the jobsite. EPD requirements ride a relay from architect to GC to subs to distributors to the plant. Along the way, substitutions, lead times, and contract choices decide which product is actually installed. If sales and sustainability teams understand this chain, last‑minute EPD scrambles turn into planned wins, not fire drills.


Start at the spec: intent vs install
Architects write intent, projects install reality. Division 01 sets procedural rules for submittals and sustainability, while each product section defines performance, acceptable manufacturers, and what proves compliance. Treat the spec like the game plan, not the finish line.
Hand‑off 1: GC bids and risk filters
General contractors price risk. They scan specs for alternates, substitutions, and required documentation. If an EPD is listed as required documentation, it becomes a pass or pause at bid time. If it is not, the GC often treats it as a later submittal item that a subcontractor must solve.
Hand‑off 2: Subs turn specs into quotes
Subcontractors live where price meets availability. In sole‑source sections, an approved submittal locks the named brand early. In open lists, subs choose among acceptable manufacturers. Missing or hard‑to‑find EPDs increase the chance another brand with a ready file gets picked. The sub is not anti‑sustainability, they are anti‑delays.
Hand‑off 3: Distributors and the availability tiebreaker
Distributors decide what ships on Tuesday. If their system cannot pull the correct EPD by SKU, plant, or mix, the order waits or the product gets swapped. Many last‑minute EPD requests start here, after procurement spots an expiring or mismatched file during order entry.
Want to streamline your EPD process?
Follow us on LinkedIn for insights that help you ensure your EPDs win specs and drive project success.
The submittal moment: where EPDs win or vanish
Submittals bundle shop drawings, product data, and sustainability documents. Reviewers check that the EPD matches the exact product, scope, and PCR. If the EPD is outdated, the reviewer may return the submital for correction. That delay can push the sub to propose an equal with clean paperwork.
Contract types change who chooses
Design bid build often locks specs earlier, but substitutions still flow through Division 01 procedures. Design build gives the GC and subs more latitude to meet performance with different brands. CM at risk can blend both. In every model, proof beats promises, so the product with a clean, verifiable EPD is easier to approve.
Why late EPD requests happen
Schedules compress, procurement finds a plant change, or a reviewer asks for the PCR version used. Sometimes the GC did not need the EPD to price the job but needs it to submit for approval. None of this is personal. It is paperwork physics meeting construction calendars.
Make your EPDs easy to buy
- Map EPDs to SKUs, plant, and options. Publish a single, stable URL per declaration and keep the PDF filename human readable.
- Cover common variants that trigger substitutions, like color systems, coatings, fasteners, or mix designs. If the variant changes impacts, document it.
- Train distributors. Give them a two‑page cheat sheet that lists where to find current EPDs and who to call for verification letters.
- Put EPD language in quotes. Example: "Quote is conditioned on acceptance of Product X with Type III, third‑party verified EPD for Plant Y; substitution may alter carbon accounting and schedule."
- Track spec wins to submittal wins. Ask sales ops to record whether the approved submittal used your brand and which EPD file was attached.
Timing and renewal traps to avoid
Most EPDs carry a five‑year validity set by the program operator, so teams should align renewal windows with peak bid seasons to avoid gaps (EPD International, 2025) (EPD International FAQ, 2025). PCRs that govern methods typically run three to five years, which means an update cycle can change the calculation rules you must follow at renewal (EPD International, 2025) (PCR Development, 2025). Some operators also remind owners to perform annual internal follow up to keep data current during the validity period, so build that check into your calendar (EPD International, 2025) (Annual Internal Follow‑Up, 2025).
Align EPD strategy with procurement behavior
Winning the spec is step one. Making your EPD effortless to retrieve, verify, and submit is how the win becomes an order. Treat distributors as part of the data chain, equip subs with precise files, and plan renewals around real project timelines. Do this, and EPDs stop feeling like surprise homework and start acting like your smoothest closer.
Frequently Asked Questions
What makes EPD requests arrive at the last minute even when we were specified early?
Schedules compress and product choices shift. Distributors often trigger the final EPD pull during order entry or submittal packaging. If the file is expired or mismatched by plant or variant, reviewers send it back, so teams ask for an updated EPD right before install.
How should manufacturers structure EPD file names to reduce submittal friction?
Use a stable URL and a readable file name that includes product family, plant, PCR ID or standard, and publication date, for example ProductX_PlantA_EN15804_PCR2019-14_2025-04.pdf. Keep the same URL when you update and archive prior versions in a clearly labeled folder.
Does a PCR expiring invalidate our current EPD on the project?
No. The EPD remains valid until its own end date. At renewal, the updated EPD must use the current PCR version. Plan the recalculation so it does not collide with peak bid or submittal periods.
Which contract type creates the most substitution risk for us?
Design build and some CM at risk arrangements allow more performance-based choices, which can increase substitutions. In design bid build, substitutions still occur through Division 01 procedures. In all cases, the brand with a clean, verifiable EPD is easier to approve.
What should sales teams capture to link spec wins to installed products?
Add two fields to the CRM: approved submittal brand and EPD file URL used. Review monthly with sustainability to spot gaps, like regions where distributors lack the correct declarations.